The project will go through a thorough review pursuant to federal and local law. Ultimately, the design team will present the project to six different boards or commissions. These include:

  • Advisory Neighborhood Commission (ANC)
  • Old Georgetown Board (OGB)
  • US Commission of Fine Arts (CFA)
  • DC Historic Preservation Review Board (HPRB)
  • DC Mayor’s Agent for Historic Preservation
  • DC Zoning Commission’s Planned Unit Development (PUD) process

Each review body has regularly scheduled public hearings.

Prior Meetings

April 3rd, 2017: ANC 2E voted 7-1 to endorse the project’s concept design

May 18th, 2017: US Commission of Fine Arts voted 7-0 to approve the concept design

September 6th, 2017: ANC 2E voted 6-0 with one abstention to endorse the project’s updated concept design

September 20th, 2017: U.S. Commission of Fine Arts voted enthusiastically 7-0 to approve the revised design concept

October 30th, 2017: ANC voted 7-1 against landmarking West Heating Plant

November 2nd, 2017: Team presented to the DC Historic Preservation Review Board

April 26th, 2018: Team concluded its design presentation to the DC Historic Preservation Review Board